Resource-constrained multi-project scheduling with activity and time flexibility

February 25, 2019 Β· Declared Dead Β· πŸ› arXiv.org

πŸ‘» CAUSE OF DEATH: Ghosted
No code link whatsoever

"No code URL or promise found in abstract"

Evidence collected by the PWNC Scanner

Authors Viktoria A. Hauder, Andreas Beham, Sebastian Raggl, Sophie N. Parragh, Michael Affenzeller arXiv ID 1902.09244 Category cs.AI: Artificial Intelligence Citations 4 Venue arXiv.org Last Checked 4 months ago
Abstract
Project scheduling in manufacturing environments often requires flexibility in terms of the selection and the exact length of alternative production activities. Moreover, the simultaneous scheduling of multiple lots is mandatory in many production planning applications. To meet these requirements, a new resource-constrained project scheduling problem (RCPSP) is introduced where both decisions (activity flexibility and time flexibility) are integrated. Besides the minimization of makespan, two new alternative objectives are presented: maximization of balanced length of selected activities (time balance) and maximization of balanced resource utilization (resource balance). New mixed integer and constraint programming (CP) models are proposed for the developed integrated flexible project scheduling problem. Benchmark instances on an already existing flexible RCPSP and the newly developed problem are solved to optimality. The real-world applicability of the suggested CP models is shown by additionally solving a large industry case.
Community shame:
Not yet rated
Community Contributions

Found the code? Know the venue? Think something is wrong? Let us know!

πŸ“œ Similar Papers

In the same crypt β€” Artificial Intelligence

Died the same way β€” πŸ‘» Ghosted