Scheduling UET-UCT DAGs of Depth Two on Two Processors

March 24, 2022 Β· Declared Dead Β· πŸ› Automation, Control, and Information Technology

πŸ‘» CAUSE OF DEATH: Ghosted
No code link whatsoever

"No code URL or promise found in abstract"

Evidence collected by the PWNC Scanner

Authors Ruzayn Quaddoura, Gassan Samara arXiv ID 2203.15726 Category cs.DS: Data Structures & Algorithms Cross-listed cs.NI Citations 1 Venue Automation, Control, and Information Technology Last Checked 4 months ago
Abstract
Given unit execution time (UET) tasks whose precedence constraints form a directed acyclic graph (DAG), the arcs are associated with unit communication time (UCT) delays. The problem is to schedule the tasks on two processors in order to minimize the makespan. Several polynomial algorithms in the literature are proposed for special classes of digraphs, but the complexity of solving this problem in general case stills a challenging open question. We propose in this paper a linear time algorithm to compute an optimal schedule for the class of DAGs of depth two.
Community shame:
Not yet rated
Community Contributions

Found the code? Know the venue? Think something is wrong? Let us know!

πŸ“œ Similar Papers

In the same crypt β€” Data Structures & Algorithms

Died the same way β€” πŸ‘» Ghosted