On the Value of Project Productivity for Early Effort Estimation

May 10, 2022 Β· Declared Dead Β· πŸ› Science of Computer Programming

πŸ‘» CAUSE OF DEATH: Ghosted
No code link whatsoever

"No code URL or promise found in abstract"

Evidence collected by the PWNC Scanner

Authors Mohammad Azzeh, Ali Bou Nassif, Yousef Elsheikh, Lefteris Angelis arXiv ID 2205.04986 Category cs.SE: Software Engineering Citations 8 Venue Science of Computer Programming Last Checked 4 months ago
Abstract
In general, estimating software effort using a Use Case Point (UCP) size requires the use of productivity as a second prediction factor. However, there are three drawbacks to this approach: (1) there is no clear procedure for predicting productivity in the early stages, (2) the use of fixed or limited productivity ratios does not allow research to reflect the realities of the software industry, and (3) productivity from historical data is often challenging. The new UCP datasets now available allow us to perform further empirical investigations of the productivity variable in order to estimate the UCP effort. Accordingly, four different prediction models based on productivity were used. The results showed that learning productivity from historical data is more efficient than using classical approaches that rely on default or limited productivity values. In addition, predicting productivity from historical environmental factors is not often accurate. From here we conclude that productivity is an effective factor for estimating the software effort based on the UCP in the presence and absence of previous historical data. Moreover, productivity measurement should be flexible and adjustable when historical data is available
Community shame:
Not yet rated
Community Contributions

Found the code? Know the venue? Think something is wrong? Let us know!

πŸ“œ Similar Papers

In the same crypt β€” Software Engineering

Died the same way β€” πŸ‘» Ghosted